Your instinct
State your homework instinct — how would you react to a mid-project addition request?
Before Phase 02, predict:
1. A change request call has three parts. Which comes first?
A change request has three parts
Handling an addition mid-project
| Part | Does what |
|---|---|
| Acknowledge the request | Confirms you heard it, before saying anything about cost or time |
| State the real impact | Cost, schedule, or both — honestly, not minimised |
| Formalise it | A change order, in writing, before the work starts |
The real Vancouver Ave. scope already includes an electric outdoor sauna — this is not a hypothetical feature invented for the exercise. Somewhere in that project’s history, a version of this exact conversation actually happened, even though the call itself, here, is rehearsed rather than transcribed.
Check what you just read.
1. Is the sauna scenario in this lesson invented, or does it reflect something real?
Saying yes, and formalising it
Handling a change request
Listen and repeat.
Match each phrase to the part of the process it belongs to. Click the phrase, then the part.
Respond to the request
Choose the response that handles the request properly.
1. A client asks mid-project to add a sauna. Best first response?
2. Once cost and schedule impact are known, what has to happen before the sauna work starts?
The call
Live, unscripted, based on a real change.
Task card
A client, mid-project on a job like Vancouver Ave., calling to ask about adding an outdoor sauna
Acknowledge, quantify the real impact, and formalise the change — all three parts, live.
- Acknowledge before you quantify anything.
- State a real impact — cost, schedule, or both — even if the exact number is invented for the exercise.
- End with the change order, explicitly, as the next step.
One check before you start.
1. This rehearsal has to include, in order:
Did all three parts happen?
Acknowledge, quantify, formalise — which of the three, if any, did you skip under pressure?
One more check before you move on.
1. According to Phase 02’s table, what does acknowledging first actually do?
Before the unit task
Homework. Choose the real project for your unit task. Know its scope well enough to write it two ways and add one genuine change to it.
One check before you go.
1. Before the unit task, you need to know your chosen project well enough to: